The Australian and Victorian Governments are delivering for Wallan, north of Melbourne, as $175 million worth of road upgrades progress.
The Watson Street Interchange Upgrade has reached the halfway mark, and it is expected to be completed six months ahead of schedule in mid-2027.
This project will deliver a new diamond interchange at the Hume Freeway to provide more direct connections to Wallan and the Wallan East Industrial precinct. Other works include installation of new traffic signals east and west of the existing Watson Street bridge over Hume Freeway, road resurfacing along Watson Street between Windham Street and McCarthy Court, and improvements to walking and cycling links along Watson Street.
Watson Street Interchange Upgrade work site (supplied by VIDA)
In addition, the Northern Highway Intersection Upgrade is on track to be completed six months early as well. This project will boost capacity on the road network in time for when then Watson Street interchange opens.
The intersection upgrade will involve the construction of additional lanes on Northern Highway in both directions as well as a second right-turn lane from Watson Street towards Wallan, and improvements to walking and cycling connections.
The two north-facing ramps will remain closed to traffic until mid-November, and motorists are encouraged to allow up to 20 minutes of additional travel time.
"These major upgrades will make it easier and safer for locals, families, businesses and freight to get around Wallan, with better connections to the Hume Freeway and less time spent in traffic," Federal Minister for Infrastructure, Transport, Regional Development and Local Government Catherine King said.
"This is a significant investment in Wallan that will ease congestion, improve safety and deliver more reliable journeys as Melbourne's north continues to grow," VIC Minister for Roads and Road Safety Paul Hamer said.
Northern Highway Intersection Upgrade site (supplied by VIDA)
Both upgrades will deliver safer, more reliable journeys for Wallan families, businesses and freight operators.
More than 1,100 jobs will be supported during the construction of the two projects.
The Australian Government has committed $90 million towards the upgrades, while the Victorian Government invests $85 million.
"The investment in these projects is something we have been waiting for.
"Together we have patiently endured the roadworks and for these to be delivered early is a welcome reward for our community," Federal Member for McEwan Rob Mitchell said.
"These important projects are on track to be delivered ahead of schedule – because Victorians deserve better roads, sooner," State Member for Kalkallo Ros Spence said.
"We're getting on with the job – delivering these critical projects six months early to make life easier for families in Wallan," State Member for Yan Yean Lauren Kathage said.
Source: Minister for Infrastructure, Transport, Regional Development and Local Government; Premier of Victoria – Media Centre; Victoria's Big Build – Big Build Roads (1, 2)
The largest wind farm in the southern hemisphere has been given the green light for development by the Victorian Government.
Following a two-stage procurement process, Downer Group has been appointed to deliver significant upgrades to Albany Airport in Western Australia.