Delivery of new 200MWh battery storage project to support 100 WA jobs

Monica Gameng   |   October 24, 2021
Synergy battery storage (cr: PV Magazine Australia)

The Western Australian Government has awarded a $155 million contract to New Horizons Ahead (NHOA) Australia to deliver a new large-scale battery energy storage system (BESS). 

The 200MWh BESS is set to become the state’s largest lithium-ion battery, with a capacity to power up to 160,000 homes for two hours. 

Consequently, NHOA has awarded a $50 million contract to local contractor GenusPlus Group to undertake engineering, procurement, construction and commissioning of the BESS. 

“We look forward to working collaboratively with NHOA as we expand our capability in the growing renewable energy sector with this significant project. We believe that our transmission and distribution market position and capability can be leveraged to become a leader in the construction and integration of renewables,” GenusPlus Group Managing Director David Riches said. 

Major construction on the project is scheduled to begin in November 2021. 

The big battery is going to be built at the decommissioned Kwinana Power Station. The project site is larger than 20 tennis courts standing side by side and will have enough space for a future expansion when needed. 

“WA’s biggest battery will support more renewable energy technologies joining the grid and help increase power stability. 

“NHOA is one of the world’s top utility-scale energy storage organisations, having installed batteries and microgrids in 26 countries. 

“Congratulations to NHOA on winning this contract and their subcontractor, Belmont business GenusPlus Group, who will require up to 100 workers for the project,” Energy Minister Bill Johnston said. 

Once operational, it will be able to store excess rooftop solar energy at daytime when demand is the lowest and rapidly discharge electricity in the afternoon and evening peak periods. 

The BESS will “help stabilise the electricity system by absorbing fluctuations caused by the increasing number of renewables on the grid”. 

The number of rooftop solar panels utilised within the state is anticipated to increase to 50 per cent by 2030. Currently, one in three households have rooftop solar panels. 

State-owned energy generator and retailer Synergy will be operating the 200MWh / 100MW battery energy storage system, which is expected to be operational by the end of 2022. 

This project is jointly funded by the Australian and Western Australian Governments, each contributing $15 million and $140 million respectively. 

“My Government has committed $140 million to build Western Australia’s biggest battery to support the main electricity grid, which serves more than 1.1 million customers. 

“This battery is crucial to WA’s sustainable energy future and a key part of the Distributed Energy Resources Roadmap. 

“There is a rapid energy transformation happening and energy storage systems such as this battery will play a key role in providing better energy outcomes for Western Australian households and businesses,” Premier Mark McGowan said. 

Source: Government of Western Australia – Media Statements; PV Magazine AustraliaGenusPlus Group; Energy Storage News 

New call-to-action

Monica Gameng
As Felix's Marketing Assistant since 2015, Monica is responsible for researching and sharing new and progressing projects within the construction and mining sectors in Australia. It's no surprise that Monica has her finger on the pulse of Australian major projects given she has produced more than 1,000 posts. She truly is an industry expert.
Follow me:

Related Articles

Projects
Two WA METRONET projects given the priority infrastructure status

Western Australia’s Thornlie-Cockburn Link and Yanchep Rail Extension - two METRONET projects - have been granted priority status by Infrastructure Australia, moving the two projects even closer towards construction.

Projects
WA's METRONET projects secure new $200m investment

Two of Western Australia’s METRONET projects receive a total of $200 million in funding from the Federal Labor, helping the projects move forward towards construction.

Projects
WA State Budget 2019-20 allocates $4.1bn for METRONET

A record $4.1 billion has been invested towards job-creating METRONET projects by the Western Australian Government through the 2019-20 State Budget.

Get the latest project news

Formerly known as the PlantMiner blog, Felix Project News is Australia's top 10 Construction blog. Join thousands of construction and mining pros getting the best content right in their inbox.
  • updates on Australia's pipeline of state and federal projects
  • fresh contract awards from major contractors and builders

If you're looking to contact us about other matters, please contact us.