BHP Billiton will be investing approximately $350 million towards the Olympic Dam smelter operations revamp in South Australia, with up to 1,300 contractors to be involved during peak construction.
According to Olympic Dam Asset President Jacqui McGill, this campaign for the smelter maintenance is going to be the biggest planned shutdown by BHP in the State.
“There will be 1,300 contractors at Olympic Dam during the peak of construction as teams work around the clock to dismantle, rebuild and upgrade integral components of the facility.
“Work is underway on site with teams preparing to dismantle old infrastructure and starting to take delivery of more than 350 material loads to support the project,” Ms McGill said.
The campaign will include:
“As always, the safety of our people and our contractors is paramount as we focus on this demanding and complex project which will help underpin stability and growth at Olympic Dam for many years to come,” Ms McGill said.
Further refinery asset maintenance works will also be done during the Olympic Dam’s planned downtime.
Works are expected to begin in August and will take more than 100 days to complete.
Source: BHP Billiton and Australian Mining
Just weeks after the beginning of the Development Phase for the High Speed Rail Newcastle to Sydney, the Australian Government has released seven major tenders for this nation-shaping transport infrastructure project.
The next phase of the Narrabri to North Star (N2NS) Inland Rail development is another step closer to construction as it secures approval from the Australian Government under the Environmental Protection and Biodiversity Act 1999.
Works have commenced on the transformation of the old Logan PCYC site into the new Logan Indoor Sports Centre, a key venue for the 2032 Brisbane Olympic and Paralympic Games and beyond.
If you're looking to contact us about other matters, please contact us.