McConnell Dowell secures contract for VIC Swanson Dock West upgrade

Monica Gameng   |   December 13, 2022
Swanson Dock West (cr: Port of Melbourne)

The first stage of works on the Swanson Dock West Remediation Project in Victoria will soon commence following the award of the contract to deliver the project. 

McConnell Dowell has been awarded the contract to undertake Stage 1 works that includes the remediation and upgrade of the existing wharf structure. 

“Swanson Dock West wharf structures must be remediated and upgraded to enable us to continue to handle container vessels for the next 50 years. 

“The existing SDW wharf is of varying ages and forms of construction. Sections of the wharf are close to or beyond the typical design life of 30 years and as a result, major remediation is needed,” Port of Melbourne CEO Saul Cannon said. 

The Swanson Dock West International Container Terminal currently has a three-berth operation. To maintain a two-berth operation while works are being carried out, Port of Melbourne developed a three-stage program that will commence construction from Berth 1. The overall project will focus on completing works from one berth to another, moving progressively towards Berth 3. 

Swanson Dock West is known as a critical International Container Terminal that features a 944-metre wharf with three container handling berths, built in several stages between the 1960s and 1980s. 

“Swanson Dock West will be the fifth project we’ve delivered for Port of Melbourne since 2017 and that means continued jobs and employment opportunities for our local staff, subcontractors and suppliers. We look forward to delivering great outcomes for the Port of Melbourne and its users,” McConnell Dowell General Manager in Victoria and Tasmania David Sims said. 

Scope of works of the Swanson Dock West Remediation Project include: 

  • Wharf remediation: 
    • Installation of new piles, including associated deck demolition and re-construction works 
    • Remediation of existing piles 
    • Seaside and Landside Crane Rail replacement at Berth 1, 2 and 3 
    • Fender beam remediation and Berth 3 transverse beam remediation 
    • Deck remediation (soffit and top) 
    • Cathodic protection on exposed re-enforced concrete elements (fender and transverse beams and soffit) 
    • Services (utilities) including remediation of drainage through sheet pile wall 
  • Retaining wall and pile remediation: 
    • Remediation (patching and encapsulation) of sheetpile wall at Berths 1, 2 and 3 
    • Remediation of Northern approach wall 
    • Replacement of protective jackets on seaward piles 
  • Bollard upgrades: 
    • Replacement of existing 50 tonne bollards with 100 tonne bollards 
    • Installation of 4 x 150 tonne bollards at Berth 1 to maintain DPW’s ability to accommodate vessels of up to 337 metres LOA on Berth 2 during the works 

The remediation project is due to be completed in 2027. 

Source: McConnell Dowell; Port of Melbourne (1, 2); Roads & Infrastructure Australia; Infrastructure Magazine 

New call-to-action

Monica Gameng
As Felix's Marketing Assistant since 2015, Monica is responsible for researching and sharing new and progressing projects within the construction and mining sectors in Australia. It's no surprise that Monica has her finger on the pulse of Australian major projects given she has produced more than 3,000 posts to date. She truly is an industry expert!
Follow me:

Recent Articles

Tenders released for High Speed Rail Newcastle to Sydney development
Projects, NSW
Tenders released for High Speed Rail Newcastle to Sydney development

Just weeks after the beginning of the Development Phase for the High Speed Rail Newcastle to Sydney, the Australian Government has released seven major tenders for this nation-shaping transport infrastructure project.

Federal approval given to Inland Rail Narrabri to North Star Phase 2
Projects, NSW
Federal approval given to Inland Rail Narrabri to North Star Phase 2

The next phase of the Narrabri to North Star (N2NS) Inland Rail development is another step closer to construction as it secures approval from the Australian Government under the Environmental Protection and Biodiversity Act 1999.

Preparation works begin on the new Logan Indoor Sports Centre
Projects, QLD
Preparation works begin on the new Logan Indoor Sports Centre

Works have commenced on the transformation of the old Logan PCYC site into the new Logan Indoor Sports Centre, a key venue for the 2032 Brisbane Olympic and Paralympic Games and beyond.

Get the latest project news

Formerly known as the PlantMiner blog, Felix Project News is Australia's top 10 Construction blog. Join thousands of construction and mining pros getting the best content right in their inbox.
  • updates on Australia's pipeline of state and federal projects
  • fresh contract awards from major contractors and builders

If you're looking to contact us about other matters, please contact us.