Planning progresses on $1.85bn VIC Next Generation Trams project

Monica Gameng   |   August 31, 2022
New generation trams (cr: Victoria State Government)

A new tram maintenance and stabling facility in Maidstone is a step closer to construction as the planning approval process for the project gets underway. 

The new facility is being built as part of the Victorian Government’s $1.85 billion investment in new generation trams. 

The tram maintenance and stabling facility will be constructed on a section of the old Victoria University site at the corner of Williamson and Hampstead roads. 

The new facility is going to be utilised to clean, maintain and stable the trams as well as house tram operations and administration staff. 

The development of the new tram facility is estimated to create up to 280 jobs, including opportunities for ongoing maintenance and the supply chain with local suppliers engaged to provide materials and services. 

“Locals have been eager to see the Maidstone site revitalised and this project will create jobs and improve services for passengers in this part of Melbourne,” Member for Footscray Katie Hall said. 

Feedback on the project is now being sought after and the community is encouraged to make a submission and give their feedback on aspects such as the use of the project site or construction impacts. 

Early works on the tram maintenance and stabling facility are anticipated to commence in early 2023. 

The more than one-billion-dollar Next Generation Trams project is the country’s largest investment in locally made trams and it is setting a standard for modern public transport through the delivery of more comfortable, accessible and energy efficient tram services. 

“Melbourne’s new next generation trams will be the most accessible, comfortable and energy-efficient trams ever, making public transport more accessible for all Victorians. 

“Building this new state-of-the-art facility will ensure the world’s largest tram network continues to run safely and reliably for years to come,” Minister for Public Transport Ben Carroll said. 

The significant investment will deliver 100 new generation trams and a new tram maintenance and stabling facility. 

The overall project is estimated to support up to 1,900 local jobs and will require a minimum of 65 per cent local content. 

Earlier this year, the contract to design, build and maintain the trams was awarded to Bombardier Transportation Australia. You can read more about the contract award here. 

The new next generation trams will start rolling out from 2026. 

Source: Victoria State Government – Media Release; Engage Victoria; Victoria State Government – Department of Transport (1, 2); Infrastructure Magazine; Rail Express; The National Tribune 

New call-to-action

Monica Gameng
As Felix's Marketing Assistant since 2015, Monica is responsible for researching and sharing new and progressing projects within the construction and mining sectors in Australia. It's no surprise that Monica has her finger on the pulse of Australian major projects given she has produced more than 1,000 posts. She truly is an industry expert.
Follow me:

Recent Articles

Significant milestone reached on M1 Pacific Motorway extension project
Projects, NSW
Significant milestone reached on M1 Pacific Motorway extension project

The M1 Pacific Motorway extension to Raymond Terrace project in New South Wales has reached a significant milestone with the final pile driven to complete foundation works on the 11 new bridges being built between Black Holl and Raymond Terrace. 

Preferred delivery partners chosen for two hospital projects in WA
Projects, WA
Preferred delivery partners chosen for two hospital projects in WA

Preferred alliance delivery partners have been announced to progress design and development of two new healthcare facilities in Western Australia. 

Thiess secures new mining services contract for Mount Pleasant Opeations
Projects, NSW
Thiess secures new mining services contract for Mount Pleasant Opeations

Thiess, a subsidiary of the CIMIC Group, has secured a six-year contract with MACH Energy for mining services at the Mount Pleasant Operation in New South Wales. 

Get the latest project news

Formerly known as the PlantMiner blog, Felix Project News is Australia's top 10 Construction blog. Join thousands of construction and mining pros getting the best content right in their inbox.
  • updates on Australia's pipeline of state and federal projects
  • fresh contract awards from major contractors and builders

If you're looking to contact us about other matters, please contact us.