Rio Tinto has awarded McConnell Dowell the contract for the construction of the Amrun Export Facility in Weipa in Far North QLD. The export facility is part of the $2.5 billion (US$1.9 billion) Amrun bauxite mining project.
Construction works for this project will include:
There will be seven 850 tonne jacket structures for the wharf and the six 1295 tonne topside modules. These heavy loads will be installed with the help of a heavy lift vessel.
Project map (source: Rio Tinto)
Provisions for all offshore mechanical and electrical works are also included in the contract awarded to McConnell Dowell.
The entire Amrun project also aims to construct a range of infrastructure that will support mining operations in the area. This will include a processing plant and a port near Boyd Bay as well as a tailing storage facility, a dam, new roads, and a ferry terminal on Hey River which will be used to transport workers from Weipa to the mine.
At least 1,100 people will be employed for this project by the peak of construction. Works are expected to begin in 2019 and will be completed within a 3-year span.
Stay up-to-date with the latest industry news and project updates by subscribing to Felix Project News today.
Construction has commenced on Neoen’s 179MW Narrogin Wind Farm in Western Australia, following the signing of a long-term power purchase agreement (PPA) with State-owned Synergy for 100 per cent of the wind farm’s generation.
The Allan Labor Government is getting on with protecting the vital connection to Phillip Island, with works now underway to restore the San Remo Bridge.
The New South Wales Government is committing an additional $250 million in the 2026-27 State Budget to get the ball rolling on the priority eastern section of the Bandon Road Upgrade in Sydney’s booming North West.
If you're looking to contact us about other matters, please contact us.