Regional WA solar and storage facility marks turning point for off-grid mines

Kerri McGrath   |   June 9, 2016

Sandfire Resources off-grid solar power and battery storage facility is now fully operational at the DeGrussa mine, 900km north of Perth, WA. 

It is the largest off-grid solar and battery storage facility in Australia, possibly the world, and is a game-changing project for energy production and storage at remote mine sites. 

The solar array at the mine covers 20 hectares, was constructed in 10 months and was delivered on budget and at peak production, it will provide 93% of all energy at the mine. 

The Australian Rewnewable Energy Agency (ARENA) supported the project with a $20.9m recoupable grant and the Clean Energy Finance Corporation committed $15m in debt finance. The remaining funding was provided by the project owner, French renewable energy developer Neoen.

ARENA CEO Ivor Frischknecht said that AREANA supports first-of-a-kind projects like this because they are crucial to increasing confidence among industry professionals, project developers, investors and financers. 

Screen_Shot_2016-06-09_at_4.42.00_PM.pngSolar panels at the DeGrussa Solar Power Project in remote Western Australia. Source: ARENA

Sandfire Managing Director, Karl Simich said the installation "draws together a number of technologies which are widely expected to have a transformational impact on the global economy over the next decade".

Over a full year, the installation is forecast to reduce the mine's carbon emissions by 15%, or 12,000 tonnes. Sandfire will benefit from more predictable power costs and anticipates potential cost savings through reduced reliance on trucked-in diesel. 

The mining industry has been watching this exciting project closely. If the benefits prove worthwhile, other miners will follow suit, exploring and adopting renewable energy technologies at remote mine sites. The installation marks a possible turning point and new era in the industry. 

It is truly exciting to see such a monumental project successfully completed in remote Western Australia. We are keen to see how the first off-grid renewable mining project goes - if you are too, stay tuned.

Source: ARENA, The Australian

 
Kerri McGrath
Kerri is a content specialist with Felix (formerly PlantMiner) and the first point of contact for the company. Her hobbies include breakfast, lunch and dinner.

Recent Articles

Next stage of $190m King Georges Rd upgrade now under construction
Projects, NSW
Next stage of $190m King Georges Rd upgrade now under construction

Works have commenced on Stage 2A of the King Georges Road upgrade in New South Wales, marking another major milestone on the $190 million project.

VIC Govt announces massive $305m redevelopment of Dandenong Hospital
Projects, VIC
VIC Govt announces massive $305m redevelopment of Dandenong Hospital

The Victorian Government is bringing better health care services closer to home to make life easier for families as it announced a major redevelopment of Dandenong Hospital.

Black Spot Program funds 44 road safety improvements across QLD
Projects, QLD
Black Spot Program funds 44 road safety improvements across QLD

Under the 2026-27 Black Spot Program, the Australian Government is committing $30.2 million to improve road safety at 44 locations across Queensland, with local councils to contribute $3.1 million towards two projects.

Get the latest project news

Formerly known as the PlantMiner blog, Felix Project News is Australia's top 10 Construction blog. Join thousands of construction and mining pros getting the best content right in their inbox.
  • updates on Australia's pipeline of state and federal projects
  • fresh contract awards from major contractors and builders

If you're looking to contact us about other matters, please contact us.